Construction Phase
The construction process started in April 2025 with early site eanbling, followed by the Geothermal well drilling and construction of the community wing. Construction of the community wing along with parking and access road to that building will be completed in December 2026.
Geothermal well drilling started in early July and finished in October. To date, all 150 wells have been drilled, grouted, completed and tested. The crew is now installing the lateral piping from the well field to the new community wing.
The prep work for footings and foundation for the new community wing building started in late August and concrete pours started in September. Steel was then started in October and will run through the end of February 2026. Roofing has started with the flat roofs nearing completion, and the standing seam roofs will follow. Exterior framing/sheathing is ongoing, as well as the rough piping for MEP.